Project Schedule

On this page you will find the project phasing schedule.

Please keep in mind this phasing schedule is a tentative schedule developed for planning purposes only. This schedule will change, possibly by a few months, one way or the other.

This schedule may vary depending on the actual condition of underground utilities, delivery of materials and equipment and weather conditions. Unforeseen issues may require extra time during construction. The schedule will be updated to reflect changes.

Please download the Phasing Map below to reference the various block numbers.

Phasing Map

Phasing Map

Block Listing

Last Updated On: January 11, 2010

Please view the schedule below to reference the various block numbers with the Phasing Map.

Phase K1A

Construction began in November 2005
Construction ended in January 2007

Phase K1B

Construction began in January 2007
Construction ended in March 2008
Block 10   -   Completed October 2007!
Block 11   -   Completed October 2007!
Block 12   -   Completed October 2007!
Block 13   -   Completed March 2008!
Block 14a -   Completed October 2007!
Block 14b -   Completed March 2008!
Block 15   -   Completed February 2008!
Block 37   -   Completed June 2007!
Block 38   -   Completed June 2007!
Block 39   -   Completed June 2007!
Block 40   -   Completed June 2007!
Block 43   -   Completed March 2008!
Block 44   -   Completed March 2008!

Phase K2A

Block 25   -   Completed April 4th, 2008
Block 26a -   Completed August 2008!
Block 26b -   Completed April 2009!
Block 27   -   Completed February 2008!
Block 28   -   Completed January 2008!
Block 29a -   Completed November 2007!
Block 29b -   Completed May 2008!
Block 30   -   Completed January 2008!

Phase K3

Block 16    -  Completed August 2008!
Block 17a  -  Completed May 2008!
Block 17b  -  Completed May 2008!
Block 17c  -  Completed May 2008!
Block 18    -  Completed October 2009!
Block 19a  -  Completed July 2008!
Block 19b  -  Completed July 2008!
Block 20a  -  Completed October 2009!
Block 20b  -  Completed October 2009!
Block 21    -  Completed November 2009!
Block 22    -  Completed November 2009!
Block 23   -   Completed October 2008!¹
Block 24   -   Completed September 2008!
Block 31   -   Completed July 2008!
Block 32   -   Completed July 2008!
Block 33   -   Completed December 2008!¹
Block 34   -   Completed February 2009!¹
Block 35   -   Completed March 2009!
Block 36   -   Completed February 2009!¹
Block 41   -   Completed September 2008!
Block 42   -   Completed September 2008!
Block 45   -   Completeed December 2009
Block 46   -   Completed September 2008!
Block 47   -   Completed May 2009!
Block 48   -   Completed April 2009!
Block 49   -   Completed August 2009!
Block 50   -   Completeed December 2009
Block 51   -   Completeed December 2009

¹ - Block status has changed since previous update